Project Details
Gantt Chart
Timeline
Budget
Target Specifications
Performance Objectives
Requisition
Gate 1
Gate 2
Gate 3
Gate 4
Gate 6
Gantt Chart
Timeline
Budget
Target Specifications
Performance Objectives
Requisition
Gate 1
Gate 2
Gate 3
Gate 4
Gate 5
Gate 6
+ / -
Gate 5 - Pilot Proving at Customer Site
Project Title
Single head belt weighre
Equipment Type
Fillers
Project Sr No
PI/FL/2
Project Proposer
Project Proposer 1
Project Lead
Ankush Joshi
Product Segment
Nonfood
Market Segment
Development Objectives
New Equipment
R & D SO No (Proto)
R & D Date (Proto)
R & D SO No (Pilot)
R & D Date (Pilot)
Project
Start Date
End Date
Plan
23-01-2023
Actual
05-11-2023
Review Date
Project Team
Please Select
Demo User
Shantanu Joshi
Amod Gokhale
Bharat Bhilare
Vishwanath Joshi
Shailendra Agashe
Pratosh Upadhayay
Pradeep Lajekar
Parag Pathwardhan
Sanket Chachad
Dhanajay K
Dipankar Dey
Chandrashekhar Pardheshi
Rushikesh Jahagirdar
Mahesh Arole
Vineet Bangalore
Atul Supekar
Vineeth Balkrishnan
Hanmant Waghmode
Vinayak Manerikar
Smita Deshmukh
Adarsh Mishra
Nikhilesh Pradhan
Pradnya Kulkarni
Pradnya Kulkarni
Sunil J
Sunil Naik
Support D
S N Sharma
Manish Kumar
Pravin Patil
Shivram Tendulkar
Barun Sahu
Rammohan Rammohan
Mrunal Joshi
Madhav Kawathekar
Sanket J
Pooja Ghorpade
Unmesh Haval
Yashwant Mali
Milind Jagtap
RAVENBHEL BIOTECH
Maheswaran Maheswaran
Girish M
Sunil Paranjpe
Meenakshi Wagh
Sanjay Salunke
Koushal Verma
Ajit Tapare
Yuvraj V
Mohan Goudelar
Manish Sharma
Ravi Kashyap
Nitin Mahadik
Prathamesh Wakankar
Prathamesh Wakankar
Nilesh Gaikwad
Nilofer Khan
Netra Atole
Nitin Nalawade
Chandrakant Rambade
Adarsh Mishra
Soumen Konai
Nita Dubal
Sameer Mahangare
Nita1 Dubal
Nita1 Dubal
Nita1 Dubal
Ajit Sutar
Satish Bhave
K Sivadas
Sanjay Mahangare
Chirag Panchal
Dutta Mahangare
Pradip Bhargude
Karthik Pathipati
Girishkumar Nair
Lalan Manjhi
Malhar Deshpande
Lalit Mahajan
S Balamurugan
Saied Khan
Deepak Mandhare
Prasad Kulkarni
Shantanu Joshi
Amar Karar
Sangita S
Sangita S
Charudatta Salunkhe
Shailesh Nishad
Bharat Bhilare
Service Service
Satish Bhave
Harish Yewale
S Merlin
Shahaji Bhosale
Vikas Jadhav
Sanjeev Gholap
Amar Karar
Sameeksha Zaware
Sameeksha Zaware
Sameeksha Zaware
Purva Kulkarni
R Maliye
Priyanka Raut
Roshan M
Pooja Bhosale
Meenakshi Pattar
Deepti Mulmule
Satish Bhave
Satish Bhave
abcd1234 abcd1234
Nilam Kulkarni
Poonam R
Pramod K
Sameeksha S Zaware
Deepti Kulkarni
Maithilee Joshi
Subodh Kulkarni
Spruha kulkarni
Siti Amizah
Shantanu Joshi
Nikhil Bhandari
Priyanka Nimare
Namrata Tare
Mayuri Hasabnis
Mayuri Hasabnis
Viraj Shirwalkar
Deepa Deshpande
Completion %
0
Timeline & Budget
Project Budget
810,000.00
Project Spend
0.00
Gate 5 Budget
35,000.00
Gate 5 Spend
0.00
Budget Approved
Yes
No
Gate 5
Start Date
End Date
Plan
Actual
Target Specifications
Specifications
UOM
Target
Achieved Gate 5
Current Nichrome
316
18
Sent For Approval
Product type
False
317
18
Sent For Approval
Product Characteristics and nature
False
318
18
Sent For Approval
Angle of repose or sliding angle
degree
False
319
18
Sent For Approval
Bulk density
gm/cm square
False
320
18
Sent For Approval
fill quantity
Gram
False
321
18
Sent For Approval
Belt weigher type
False
322
18
Sent For Approval
Filling Range
Gram
False
323
18
Sent For Approval
Machine name
False
324
18
Sent For Approval
Accuracy
Gram
True
325
18
Sent For Approval
fill time
mili seconds
False
326
18
Sent For Approval
seal time
mili seconds
False
327
18
Sent For Approval
cycle time
mili seconds
False
328
18
Sent For Approval
Pouch size W x L X seal width
Milimeter
False
329
18
Sent For Approval
Bucket volume
Centimeter
False
330
18
Sent For Approval
Auxillary bucket volume
Centimeter
False
331
18
Sent For Approval
Load cell capacity
Centimeter
False
332
18
Sent For Approval
Hopper capacity
Centimeter
True
333
18
Sent For Approval
Material of contact parts
False
334
18
Sent For Approval
Material of construction
False
335
18
Sent For Approval
Power required
Feet
False
336
18
Sent For Approval
supply voltage
Milimeter
False
337
18
Sent For Approval
Power consumption
Miligram
False
338
18
Sent For Approval
Automation make
False
339
18
Sent For Approval
PLC make
False
340
18
Sent For Approval
Pneumatic make
False
341
18
Sent For Approval
Air consumption
Microgram
False
342
18
Sent For Approval
MHS type
False
343
18
Sent For Approval
Feed rate
Kilogram
True
344
18
Sent For Approval
weight
Gram
False
345
18
Sent For Approval
foot printW x L x H
Ounce
False
Task List
1.1
1.01.01
1.1.1.1
Task
Post inspection of parts received
Start Date
Duration
Date
22 Apr 2022
Completion %
50
Date
25 Apr 2022
1.01.02
Task
Post inspection of parts received
Start Date
Duration
Date
22 Apr 2022
Completion %
50
Date
25 Apr 2022
1.2
1.02.01
1.2.1.1
Task
Post inspection of parts received
Start Date
Duration
Date
22 Apr 2022
Completion %
50
Date
25 Apr 2022
1.3
Task
Post inspection of parts received
Start Date
Duration
Date
22 Apr 2022
Completion %
50
Date
25 Apr 2022